7th Avenue South Bike Boulevard Nearing Completion

A few more weeks and the new Bike Boulevard along 7th Avenue South should be finished and full open.

The 7th Avenue Bike Boulevard is only a few weeks away from being fully complete. Project Manager Robert Kovacs telling our radio station crews have about three intersections to complete and weather-permitting, it should all be done by the first week of November. He says the intersections of 4th, 6th, and 8th streets along 7th Avenue South are the ones which need to be completed yet as well as the the new specialized traffic lights at the intersection of 13th Street and 7th Avenue South. Kovacs says the Bike Boulevard between Mayor Magrath Drive and 13th Street is being used already by cyclists, however there is still road painting which needs to be finished up. - Pat Siedlecki